Sellafield, in Cumbria, is now estimated to cost £79.1bn to clean up, but the NDA warned that the total would “increase significantly next year” once it had fully assessed a new “performance plan” for the site.
It says it has “reviewed a number of scenarios with a range of possible outcomes” and found that “the estimated cost could have a potential range from £88bn to £218bn”.
The figure of £110bn is on an “undiscounted” basis. Once discounted, the total is £65bn.